Saturday, February 17, 2007

Memorial Stadium Update from Sandy Barbour

(This came to Alumni via email)

 

Dear Friend of Cal Athletics:

 

I want to ensure you that despite a recent ruling granting a preliminary injunction against the entirety of the Southeast Campus Integrated Projects, including the proposed Student-Athlete High Performance Center, we remain completely committed to the project. We fully believe it is only a matter of time before our state-of-the-art facility is completed adjacent to historic Memorial Stadium.

 

We consider Judge Barbara Miller's decision to postpone work on the project until a summer trial only a temporary setback and that we will succeed on the merits of the case. The suits brought by the City of Berkeley, the California Oak Foundation and the Panoramic Hill Association are only serving to delay building a center that will improve the life safety and everyday conditions for the hundreds of Golden Bear student-athletes, coaches and staff who use Memorial Stadium on a daily basis.

 

The court, which had only a few days to review a large set of complex issues, had concerns about the project's conformity with CEQA (California Environmental Quality Act) and APZA (Alquist-Priolo Fault Zoning Act). Compliance with these two state statutes has been at the forefront of our planning process from the very beginning. With our team of expert geologists and engineers, we believe we have fully complied with the law and will prevail when the court case is heard.

 

Last week, after a short hearing in Superior Court, Judge Miller finalized the Preliminary Injunction prohibiting us from “taking any further action to implement the Southeast Campus Integrated Projects including … the Student Athlete High Performance Center, if such action would result in change or alteration to the  physical environment.” This ruling does allow us to continue the essential design, planning, soils testing, contracting and bidding elements of the High Performance Center and preserves the University's authority to manage and operate the site as it has done for decades.

 

The High Performance Center was designed with a budget of $125 million, and we have raised nearly $100 million so far. Over the ensuing months, we will continue our planning and fundraising for the High Performance Center so that when we do get the go-ahead, we will be ready to move forward as soon as possible. Once we are able to break ground, we anticipate construction lasting 20-24 months.

 

We cannot let the plaintiffs' actions or the preliminary injunction slow down our momentum for this important first phase of the Memorial Stadium renovation. However, with construction costs in the Bay Area constantly rising, the delay means an increased cost to the project, although it is hard to give an exact figure at this time.

 

We are currently developing a new Web site for the stadium project that will contain press releases, frequently asked questions, renderings, video statements from UC staff, and updates on fundraising and naming opportunities. This site will be accessible through CalBears.com, and we expect to have it completed by the end of the month.

 

If you have any questions concerning the Student-Athlete High Performance Center, please contact the Athletic Development office at (510) 642-2427 or via email at bearback@berkeley.edu.

 

Go Bears!